What is the difference between target costing and kaizen costing?

GradeHunt_TeamGradeHunt Team · · CMA Final

CMA Final SCM theory questions ask about target costing and kaizen costing. They both reduce cost, so how are they different?
target costingkaizen costingstrategic cost managementcma final

1 answer

0
Both aim at lower costs, but they act at different stages of a product's life. Target costing: - Used at the design and development stage, before production starts. - Target cost = expected selling price - required profit margin. - The product is designed so that its cost does not exceed the target cost, using value engineering and cross-functional teams. - Market-driven: the price the customer will pay is the starting point. - Most cost is locked in at design, so this is where large savings are possible. Kaizen costing: - Used at the manufacturing stage, after the product is launched. - Aims at small, continuous cost reductions period after period. - Targets are set for each period (for example, a 2% reduction a month) and achieved through process improvements suggested largely by workers on the shop floor. - Focus is on the production process, not the product design. Key differences in one line each: - Stage: design vs production. - Size of change: large, one-time design changes vs small, continuous improvements. - Who drives it: design and engineering teams vs operators and supervisors. - Starting point: market price vs current actual cost. How they fit together: target costing sets a cost the product can reach, and kaizen costing keeps lowering it after launch. Many firms use both. Exam tip: end a theory answer with this link between the two. It shows you understand how the two methods work together, not just the definitions.
GradeHunt_TeamGradeHunt Team · 0 pts ·