0

How do I calculate material cost variance, material price variance and material usage variance?

GradeHunt_TeamGradeHunt Team · · CMA Inter

Standard costing in CMA Inter Management Accounting confuses me. I always get the favourable and adverse signs wrong, and I'm not sure whether to use standard quantity for actual output or the budgeted quantity. Can someone explain with one example?
standard costingmaterial cost variancematerial price variancematerial usage variance

1 answer

0
Formulas: Material Cost Variance (MCV) = (SQ x SP) - (AQ x AP) Material Price Variance (MPV) = (SP - AP) x AQ Material Usage Variance (MUV) = (SQ - AQ) x SP MCV = MPV + MUV SQ = standard quantity for the ACTUAL output, not the budgeted quantity. This is the most common mistake. SP = standard price, AQ = actual quantity used, AP = actual price. Sign rule: with standard written first in each formula, a positive answer is Favourable (F) and a negative answer is Adverse (A). Worked example: Standard: 2 kg per unit at Rs 50 per kg Actual output: 1,000 units Actual material used: 2,100 kg at Rs 48 per kg SQ = 1,000 x 2 = 2,000 kg SQ x SP = 2,000 x 50 = Rs 1,00,000 AQ x AP = 2,100 x 48 = Rs 1,00,800 MCV = 1,00,000 - 1,00,800 = -800, so Rs 800 (A) MPV = (50 - 48) x 2,100 = Rs 4,200 (F) MUV = (2,000 - 2,100) x 50 = -5,000, so Rs 5,000 (A) Check: 4,200 (F) - 5,000 (A) = 800 (A). It matches. Reading the result: the buyer saved Rs 2 per kg, but production used 100 kg more than the standard. One possible story is cheaper, lower-quality material causing more wastage. So the two variances may be linked, and responsibility for them is not always separate (price usually sits with purchase, usage with production). If the quantity purchased differs from the quantity used, the price variance can be computed on the quantity purchased, at the time of purchase. Follow what the question asks. Next step: the usage variance can be split further into mix and yield variances when more than one material is used.
GradeHunt_TeamGradeHunt Team · 0 pts ·